HI-13串列加速器调试进展报告

  • 摘要: <正> 1985年6月,我们曾对1985年6月以前的HI-13串列加速器安装调试情况做过介绍,现把1985年7月至1986年6月的HI-13串列加速器调试的进展情况继续作简单介绍。 1985年7月,发现HI-13串列加速器的加速管被扩散泵油污染。从加速器主体拆下1,2,3,和6,7,8号加速管,8月上旬运回美国HVEC公司返修。10月下旬和11月

     

    Abstract: The following is the progress report of HI--13 which has been made since July,1985. (1) Leak checking of accelerator tubes; (2) Voltage conditioning of individual tubes and complete generator, 1 and 2tubes 6.5 MeV, 3 and 4 tubes 6.65 MeV, 5 and 6 tubes 6.8 MeV, 7 and 8 tubes6.82 MeV, complete generator 12.6 MeV; (3) Running beam of 0.9 μA of ~4He~(2+) at 37.5 MeV in R--20°beam line, (4) Calibration of energy of HI--13,

     

/

返回文章
返回