国家同步辐射实验室工程进展
STATUS REPORT OF HESYRL PROJECT
-
摘要: <正> 我们曾在原子能科学技术1985和1986两年的粒子加速器专刊上介绍了国家同步辐射实验室工程的设计和进展。由于经费困难,该工程的进度已经放慢。1986年下半年国家有关主管部门通知调整国家同步辐射实验室工程计划。把同步光源的出光时间推迟一年,即1989年底;光源出光时,同时建成的光束线和实验站数目减至一条线、一个站,即光Abstract: The present status of HESYRL (Hefei National Synchrotroh Radiation Labora-tory) project is reported. The civil construction will be completed very soon.The installation of the 200 MeV Linac injector has started and will be completedin this september. The storage ring components are under production after proto-type tests. The storage ring installation will start in the middle of next year andcommissioning is scheduled in 1989.