  • 摘要: 作为国家科技重大专项的高温气冷堆核电站示范工程(HTR-PM)在山东荣成正式开工建设,为验证HTR-PM堆芯出口热气混合结构是否满足混合要求,利用建立的缩比模型实验台架,进行了两支路(热气支路及冷气支路)3个系列工况的实验,实验包括:定流量变温差实验、定温差变流量实验、定温差与总流量变流量比实验。通过对实验数据进行分析,得出两支路工况下,热气混合结构的混合效率均在98%左右。通过与蒸汽发生器的入口温度要求进行对比分析,可得出在考虑不经过堆芯的漏流的两支路工况条件下,HTR-PM堆芯出口的热气混合结构能满足热混合的要求。

     

    Abstract: The plant of pebble-bed module high temperature gas-cooled reactor (HTR-PM), one of Chinese National S&T Major Projects, started the first concrete date (FCD) in Rongcheng, Shandong Province. A scale model experiment installation was constructed to verify the mixing performance of the hot gas mixing structure at HTR-PM reactor outlet. The experiments were carried out on the installation which included three series of conditions: Constant flow and variable temperature differences, constant temperature difference and variable flows as well as constant temperature difference and total flow and variable flow ratios. The mixing performance of the hot gas mixing structure is around 98% in all two-channel working conditions according to the data collected in the experiments. By comparing with the requirement of the inlet temperature for steam generator, it is concluded that the hot gas mixing structure at HTR-PM reactor outlet can meet the mixing requirement under two-channel working condition if the leakage out of the reactor core is considered

     

/

返回文章
返回