基于耦合CFD-FEM方法的严重事故下RPV蠕变失效风险评估

Risk Assessment of Creep Failure for RPV under Severe Accident Condition Based on Coupled CFD-FEM Method

  • 摘要: 核电站严重事故发生后,反应堆压力容器(RPV)的剩余固壁在高温差、内压、熔池重量等的作用下可能发生蠕变失效。本文以CPR1000 RPV为研究对象,基于FLUENT软件二次开发求解反应堆压力容器下封头烧蚀温度场,然后基于ANSYS Workbench开展耦合CFD-FEM力学分析,求解严重事故下RPV烧蚀温度场稳定后72 h内的等效应力、等效塑性应变和等效蠕变应变,并评估了RPV的蠕变失效风险。结果表明:当堆坑注水等措施投运后,RPV剩余固壁在72 h内不会发生蠕变失效和塑性变形失效,有效卸压可明显提升RPV结构完整性的安全裕度。

     

    Abstract: After a reactor core melt accident, creep failure may occur in the residual solid wall of the reactor pressure vessel (RPV) under the influence of high temperature difference, internal pressure and the weight of the molten pool. In this work, the CPR1000 RPV was used as a research object. The ablation temperature field of the lower head of RPV was solved through the secondary development of the FLUENT software. And then, a CFD-FEM coupling analysis was carried out based on ANSYS Workbench software. The equivalent stress, the equivalent plastic strain and the equivalent creep strain of the RPV within 72 h under severe accident after the wall ablation and temperature field distribution formed stably were calculated. The risk of creep failure of the RPV was evaluated. The results show that when the reactor pit water injection measure puts into operation, the residual solid wall of the RPV will not experience creep failure and plastic deformation failure within 72 h, and besides, the pressure relief can significantly increase the safety margin of the structural integrity of the RPV.

     

/

返回文章
返回